Before
To begin the process a small hole is drilled through the wall and a rod is driven out.
During
A hole is made in the yard for the earth anchor to be attached to the rod.
During
The soil is dug out from the wall to ensure the rods are going into the ground proper.
During
The rods are then driven through the wall into the ground.
During
An earth anchor is installed and attached to the rod.
After
Once all the pieces are in place the ground is backfilled.
After
Once completed the HideAway Anchor cover is put on.
After
Since the sidewalk was removed to install the Earth Anchors, concrete was poured and the sidewalk was restored.
After
A SmartJack was also installed for extra support.